On January 23rd, 2024, a significant milestone was achieved in the removal of the Copco 1 dam on the Klamath River. A 12 ft. diameter tunnel was successfully blasted at the base of the dam, marking the start of the reservoir drawdown process. This action led to the release of an estimated 4000 cubic feet per second of water and sediment.
During the previous summer, a significant effort was made to prepare for the dam removal. Crews blasted a 90 ft. adit tunnel at the base of the dam and inserted pipe, which was further reinforced with boulders and 1000 yards of concrete.
To fully set the river free, 800 lbs. of dynamite was deployed to blast the remaining concrete plug. As a result, a surge of water traveled several miles beyond the former Copco 2 dam and the renowned Wards Canyon, which had largely been devoid of water for a century. The unleashed flow eventually found its way into newly formed river channels within the former Iron Gate Reservoir.
This exciting development paves the way for the complete removal of the Copco 1 dam by the end of 2024.
Side Note:
- KRRC Enlisted Powerful Consulting Firm to Navigate Klamath Dam Removal Challenges“CEA’s client base reads like a who’s who of environmental power players, their involvement signals the level of complexity and importance of the Klamath project.” In a strategic move to address the complex issues surrounding the Klamath River dam removal project, the Klamath River Renewal Corporation (KRRC) partnered with CEA Consulting, a San Francisco-based firm… Read more: KRRC Enlisted Powerful Consulting Firm to Navigate Klamath Dam Removal Challenges
- Meeting the Demand: The Essential Role of Current and Future Health ProfessionalsUnited Health Foundation Diversity in Health Care Scholarship Applications Due October 31, 2024 By Anne Yau Senior Vice President, Social Responsibility, UnitedHealth Group and President, United Health Foundation Experience shows that when patients receive care from health providers who speak their language or understand their cultural needs, they are more responsive and engaged. This can lead to… Read more: Meeting the Demand: The Essential Role of Current and Future Health Professionals
- Klamath River Project Adult Fish Counting Facility Update – October 11, 2024The California Department of Fish and Wildlife has released its latest in-season update for the Klamath River Project Adult Fish Counting Facility. This update provides preliminary 2024 returns of Fall-run Chinook Salmon and Coho Salmon to each counting facility. Operational Status and Counts Shasta River Bogus Creek Scott River Jenny Creek Shovel Creek Station Locations… Read more: Klamath River Project Adult Fish Counting Facility Update – October 11, 2024
- Klamath Basin End of the 2024 Irrigation SeasonThe K.I.D. Board of Directors approved a 15 October shut down of the A Canal to begin emergency repairs and other maintenance tasks. On average, K.I.D. diverts over 220,000 acre-feet of water through the A Canal to fulfill its legal and contractual obligations to farmers. In 2024, only 130,000 acre-feet of water (59%) will be diverted… Read more: Klamath Basin End of the 2024 Irrigation Season
- CHSRA District 1 Rodeo #2 Full Results: McArthur, CA (October 4-6, 2024)The California High School Rodeo Association (CHSRA) District 1 held its second rodeo of the season in McArthur, CA, from October 4-6, 2024. Young cowboys and cowgirls from across Northern California showcased their skills in various events. Here are the full results for each category: Riding Events Bareback Riding (2 entries) Saddle Bronc Riding (1… Read more: CHSRA District 1 Rodeo #2 Full Results: McArthur, CA (October 4-6, 2024)